What Does Contract ‘Repudiation’ and ‘Breach’ Mean for Builders?

6 Aug 2024

Introduction

Understanding contract repudiation and breach is crucial for builders. This article explores these concepts, providing practical insights for when relationships with owners break down irretrievably. Even with excellent quality management, disputes can arise. Here, we delve into what happens when an owner retakes possession of their land, changes the locks, or otherwise communicates that the contract is at an end, leaving the builder pondering their next steps.

The Tricky Concept of Repudiation

Repudiation occurs when one party shows an intention to no longer be bound by the contract. This can happen through actions like retaking possession, changing the locks, or telling the builder to leave the site. The test of repudiation is whether the action or conduct amounts to “evincing an intention to no longer be bound by the contract.”

Case Study: Carr v JA Berriman Pty Ltd

A significant case illustrating repudiation is Carr v JA Berriman Pty Ltd (1953). In this case, Carr, the owner, failed to clear the site as required and also breached his promise about steel supply. These non-essential breaches, taken together, showed Carr’s intention to not honor the contract, giving Berriman the right to rescind on the ground of repudiation.

Detailed Analysis of Carr v JA Berriman Pty Ltd

The Carr v JA Berriman case concerned an owner and a builder contracted to build a factory. Carr failed to clear the site by the agreed date, and although this was a breach, it was not essential enough to terminate the contract. However, Carr also breached another term by taking over the responsibility for supplying and fabricating steel, which impacted Berriman’s ability to pay subcontractors. The court found that these repeated breaches indicated Carr’s lack of intention to fulfill the contract, leading to repudiation.

Breaches of Essential and Innominate Terms

Contracts can end due to substantial breaches of essential or innominate terms. The importance of these terms is highlighted in the case Tramways Advertising Pty Ltd v Luna Park (1938).

Judge’s Quote: “Whether it appears from the general nature of the contract, or from some particular terms, that the promise is of such importance that the party would not have entered into the contract unless he had been assured of a strict or substantial performance of the promise.”

Essential Terms

An essential term is one that goes to the root of the contract. Breaching such a term gives the other party the right to terminate the contract.

Innominate Terms

Innominate terms do not follow the same test. Whether breach of an innominate term gives rise to a right to terminate depends on whether the breach causes substantial loss, despite not being essential at the time of contract formation.

Notice of Default and Notice of Termination

Properly ending a contract involves serving an initial notice of default, detailing the breach and allowing the other party to rectify it. If unresolved, a notice of termination follows. This procedure ensures due process and legal compliance.

Serving the Notice of Default

The preliminary notice sets out the contract breach and requires rectification within the set time allowed by the contract. If the default is not remedied, the non-defaulting party reserves the right to serve a notice of termination.

Serving the Notice of Termination

The termination notice ends the contract if the breach remains unrectified. This step often leads to legal disputes if significant monies are owed on either side.

Wrongful Termination Risks

Owners who retake possession without following proper procedures may commit wrongful termination or repudiation, exposing themselves to legal challenges. Even with proper notice, termination could still be unlawful if the terminating party is in breach or if the grounds for termination are unmeritorious.

Non-Contractual Claims: Quantum Meruit

Builders can claim damages on a “quantum meruit” basis, reflecting the value of work done. Recent rulings, like Mann v Paterson Constructions Pty Ltd [2019], cap these claims to the agreed contract price, stressing the importance of following contractual variation processes.

Quantum Meruit Explained

Quantum meruit means “as much as he has earned.” It allows builders to claim the reasonable value of work performed, especially if the contract is wrongfully terminated. This claim can sometimes exceed the contract price but is now capped to the agreed price per recent High Court decisions.

Importance of Documentation

Maintaining a thorough paper trail, including all invoices and receipts, is crucial. These documents support damage calculations and demonstrate incurred costs. Builders should keep records from both subcontractors and suppliers, not just invoices served on the owner. Proper documentation is essential for proving the costs incurred and the value of work done, especially in legal disputes.

Lost Profit Margin on Remaining Work

Builders can also claim for the lost profit margin on works yet to be completed under the contract. For instance, if an owner wrongfully terminates at the end of the Lock Up stage, the builder can claim the lost profit for the Fixing and Completion stages. This is a vital consideration for builders facing wrongful termination.

Owner’s Right to Claim Damages

On the flip side, if a builder repudiates the contract or is validly terminated, the owner can claim damages. This often involves engaging a second contractor to complete the works, which usually costs more than the balance left in the contract price. The additional costs can be charged back to the original builder as damages, leading to potential court or tribunal disputes.

Importance of Legal Advice

Given the complexities involved in determining repudiation, breach, and the proper termination process, seeking legal advice is paramount. Mistakes in these areas can lead to significant financial and legal repercussions. Legal professionals can help navigate these issues, ensuring that all actions are legally sound and defensible.

Conclusion

Understanding the nuances of contract repudiation and breach is crucial for builders. Properly addressing these issues requires meticulous attention to detail, comprehensive documentation, and often, legal expertise. By following the correct procedures and seeking professional advice, builders can protect their interests and navigate the challenges of contract disputes effectively.

Contact Lovegrove & Cotton Lawyers

For thirty years, Lovegrove & Cotton have represented builders, building surveyors, and building practitioners in Melbourne, Canberra, Sydney, and Queensland. If you need legal assistance, contact us via our website or email enquiries@lclawyers.com.au.

Author: Justin Cotton, Director, Lovegrove & Cotton – Construction and Planning Lawyers

About Justin Cotton

Justin Cotton is a leading Australian construction lawyer and widely respected in the building fraternity. He has been a member of the HIA Industrial Relations and Legal Services Committee and the Regional Executive Committee for the HIA Victorian Chapter for a long time. Lovegrove & Cotton can help practitioners resolve any type of building dispute and are preeminent in the area of building practitioner advocacy.

For more detailed information, refer to the original article here.