Understanding contract repudiation and breach is crucial for builders. This article explores these concepts, providing practical insights for when relationships with owners break down irretrievably. Even with excellent quality management, disputes can arise. Here, we delve into what happens when an owner retakes possession of their land, changes the locks, or otherwise communicates that the contract is at an end, leaving the builder pondering their next steps.
The Tricky Concept of Repudiation
Repudiation occurs when one party shows an intention to no longer be bound by the contract. This can happen through actions like retaking possession, changing the locks, or telling the builder to leave the site. The test of repudiation is whether the action or conduct amounts to “evincing an intention to no longer be bound by the contract.”
Case Study: Carr v JA Berriman Pty Ltd
A significant case illustrating repudiation is Carr v JA Berriman Pty Ltd (1953). In this case, Carr, the owner, failed to clear the site as required and also breached his promise about steel supply. These non-essential breaches, taken together, showed Carr’s intention to not honor the contract, giving Berriman the right to rescind on the ground of repudiation.
Detailed Analysis of Carr v JA Berriman Pty Ltd
The Carr v JA Berriman case concerned an owner and a builder contracted to build a factory. Carr failed to clear the site by the agreed date, and although this was a breach, it was not essential enough to terminate the contract. However, Carr also breached another term by taking over the responsibility for supplying and fabricating steel, which impacted Berriman’s ability to pay subcontractors. The court found that these repeated breaches indicated Carr’s lack of intention to fulfill the contract, leading to repudiation.
Breaches of Essential and Innominate Terms
Contracts can end due to substantial breaches of essential or innominate terms. The importance of these terms is highlighted in the case Tramways Advertising Pty Ltd v Luna Park (1938).
Judge’s Quote: “Whether it appears from the general nature of the contract, or from some particular terms, that the promise is of such importance that the party would not have entered into the contract unless he had been assured of a strict or substantial performance of the promise.”
Essential Terms
An essential term is one that goes to the root of the contract. Breaching such a term gives the other party the right to terminate the contract.
Innominate Terms
Innominate terms do not follow the same test. Whether breach of an innominate term gives rise to a right to terminate depends on whether the breach causes substantial loss, despite not being essential at the time of contract formation.
Notice of Default and Notice of Termination
Properly ending a contract involves serving an initial notice of default, detailing the breach and allowing the other party to rectify it. If unresolved, a notice of termination follows. This procedure ensures due process and legal compliance.
Serving the Notice of Default
The preliminary notice sets out the contract breach and requires rectification within the set time allowed by the contract. If the default is not remedied, the non-defaulting party reserves the right to serve a notice of termination.
Serving the Notice of Termination
The termination notice ends the contract if the breach remains unrectified. This step often leads to legal disputes if significant monies are owed on either side.
Wrongful Termination Risks
Owners who retake possession without following proper procedures may commit wrongful termination or repudiation, exposing themselves to legal challenges. Even with proper notice, termination could still be unlawful if the terminating party is in breach or if the grounds for termination are unmeritorious.
Non-Contractual Claims: Quantum Meruit
Builders can claim damages on a “quantum meruit” basis, reflecting the value of work done. Recent rulings, like Mann v Paterson Constructions Pty Ltd [2019], cap these claims to the agreed contract price, stressing the importance of following contractual variation processes.
Quantum Meruit Explained
Quantum meruit means “as much as he has earned.” It allows builders to claim the reasonable value of work performed, especially if the contract is wrongfully terminated. This claim can sometimes exceed the contract price but is now capped to the agreed price per recent High Court decisions.
Importance of Documentation
Maintaining a thorough paper trail, including all invoices and receipts, is crucial. These documents support damage calculations and demonstrate incurred costs. Builders should keep records from both subcontractors and suppliers, not just invoices served on the owner. Proper documentation is essential for proving the costs incurred and the value of work done, especially in legal disputes.
Lost Profit Margin on Remaining Work
Builders can also claim for the lost profit margin on works yet to be completed under the contract. For instance, if an owner wrongfully terminates at the end of the Lock Up stage, the builder can claim the lost profit for the Fixing and Completion stages. This is a vital consideration for builders facing wrongful termination.
Owner’s Right to Claim Damages
On the flip side, if a builder repudiates the contract or is validly terminated, the owner can claim damages. This often involves engaging a second contractor to complete the works, which usually costs more than the balance left in the contract price. The additional costs can be charged back to the original builder as damages, leading to potential court or tribunal disputes.
Importance of Legal Advice
Given the complexities involved in determining repudiation, breach, and the proper termination process, seeking legal advice is paramount. Mistakes in these areas can lead to significant financial and legal repercussions. Legal professionals can help navigate these issues, ensuring that all actions are legally sound and defensible.
Conclusion
Understanding the nuances of contract repudiation and breach is crucial for builders. Properly addressing these issues requires meticulous attention to detail, comprehensive documentation, and often, legal expertise. By following the correct procedures and seeking professional advice, builders can protect their interests and navigate the challenges of contract disputes effectively.
Contact Lovegrove & Cotton Lawyers
For thirty years, Lovegrove & Cotton have represented builders, building surveyors, and building practitioners in Melbourne, Canberra, Sydney, and Queensland. If you need legal assistance, contact us via our website or email enquiries@lclawyers.com.au.
Author: Justin Cotton, Director, Lovegrove & Cotton – Construction and Planning Lawyers
About Justin Cotton
Justin Cotton is a leading Australian construction lawyer and widely respected in the building fraternity. He has been a member of the HIA Industrial Relations and Legal Services Committee and the Regional Executive Committee for the HIA Victorian Chapter for a long time. Lovegrove & Cotton can help practitioners resolve any type of building dispute and are preeminent in the area of building practitioner advocacy.
For more detailed information, refer to the original article here.
Disclaimer
This article provides general information and is not legal advice. For specific legal guidance, contact Lovegrove & Cotton Lawyers.
Image Acknowledgements:
The digital renders used in this article were developed collaboratively by Lovegrove & Cotton and ChatGPT. The photo images that are not the digital renders are stock images sourced from Shutterstock.

The vexed question of who has standing over common property building defects in an apartment building is more pertinent than ever, in these days of more inhabitants of high-rise buildings administered by Owners Corporations.
It is also more relevant in these days of higher rainfall levels across Australia and including in Victoria where once, only little more than a decade ago, there was concern about an ongoing drought.
Waterproofing and leaky building defects, afflicting balconies, ceilings, and common area basements are now frequent hallmarks of domestic building claims in Victoria. Regularly encountered common area problems can be façade issues with render or combustible cladding, water ingress issues with pipes in wall cavities and water leaks from balconies, and cracking and water ingress in basements with slabs, columns and beams.

It is important to note that, save for cladding claims that may have a longer 15-year limitation period, the Owners Corporation will be subject to the usual 10 year limitation period (counted from the date of the Occupancy Permit) to issue legal proceedings against the original builder and other construction practitioners (eg designers) in building defect claims.
It is not a rare situation for building defect claims in Victoria to involve the Owners Corporation as the Applicant for the common property defects, and for various named lot owners as co-Applicants in relation to defects located on or affecting their private lots / apartments.
There is no special resolution needed (obviously) for private lot owners to bring legal proceedings for defects located in, or damage sourced in, their private apartments. However, for building defects located in or on the common property, only the Owners Corporation has legal standing to initiate such legal proceedings for redress.
Given that an Owners Corporation has a duty to repair and maintain the common property under the Owners Corporation Act 2006 (section 46) they may indeed have a duty to initiate legal proceedings against the parties responsible for such defects, or instead have the lot owners pay for such defect repairs directly (if there is not going to be legal proceedings against the builder or other parties).
Special Resolutions
In order to authorise an Owners Corporation to issue legal proceedings it is necessary to obtain a “Special Resolution” from the lot owner members of the Owners Corporation, either by vote at a meeting (AGM or SGM) or by ballot. A Special Resolution requires 75% of votes in favour, out of all lots entitled to a vote on the issue. Section 18 of the Act refers to the need for a Special Resolution in these circumstances.
If it is not possible to get a Special Resolution of votes in favour at the first attempt, at a meeting or by ballot, there can be some leeway on this, for instance by having an interim special resolution. However, to do this the Owners Corporation must satisfy the requirements in section 97 of the Owners Corporation Act 2006 (“the OC Act”) which is not always easy to do if there is not a quorum for the vote or if the vote in favour is not at least 50% of the total votes of all lots affected by the Owners Corporation.
Based on the precedent case in the Victorian Supreme Court of Body Corporate No 1 / PS40911511E St James Apartments v Renaissance Assets Pty Ltd [2004] VSC 438, the Supreme Court held that the Owners Corporation as a legal entity is the registered proprietor of the common property and was the “building owner” for the purposes of the OC Act in relation to the common property.
This meant that only the Owners Corporation, which owns the common property on behalf of the various lot owner members of the Owners Corporation, has legal standing to take legal proceedings in relation to common property.
So far it is relatively uncontroversial. It can be a complex question though on where exactly lies the demarcation between private property versus common property, when deciding who has standing to take legal action over apartment building defects. This is particularly so in relation to the balconies of private apartments, at least in the Victorian setting.
One can have regard to expert reports and the Plan of Subdivision to try to work out the separating line between private and common property in an Owners Corporation building. These tend to be more technical questions and legal interpretations are really confined to previous case law.
Often a Plan of Subdivision will show the boundary as the median line halfway between the two faces of the external and internal wall, or halfway between the ceiling of the topmost apartment and the roof. Needless to say, the roof of an apartment building will be seen as common property, as will the basement.

In relation to apartment balconies, the tiled floor of the balcony has traditionally been seen as private property appurtenant to the lot, while the inside face of the balustrade is similarly seen as private, but the outside balustrade face presenting to the street is seen as common property.
Between Australian jurisdictions, there have been differing case decisions on where the separating line is between common versus private property on apartment balconies. This is a critical question because it obviously affects the question of who has legal standing to bring legal proceedings.
It is generally accepted that the slab beneath and supporting a balcony is part of the infrastructure and with a purely functional purpose, and will be common property, while the tiles on the balcony floor are decorative and not functional and are private property.
In the New South Wales decision of The Owners SP 35042 v Seiwa Australia Pty Ltd [2007] NSWCA 272, it was held (lines 37-39) that the waterproofing membrane laid under the tiles on a balcony formed part of the common property for the building.
Also, in the ACT Supreme Court decision of The Owners Units Plan No 1917 v Koundouris [2016] ACTSC 96 (13 May 2016) the Judge declared at paragraph 580 that the waterproofing should most appropriately be treated as a part of the slab “because it is a functional rather than decorative treatment to the slab and is practically integrated with it. It is distinct from a finish such as tiling or painting.”
In contrast, in Victoria at the VCAT level a differing conclusion has been reached on where the separating line is between common versus private property and whether or not the waterproofing membrane should be regarded as private or common property.
There is little doubt across the jurisdictions that the floor tiles on a balcony, which can present as delaminating or lifting in many defect situations, are regarded as the private property of the lot owner. That said, the actual problem leading to the manifestation of distress is sourced in the waterproofing, or the lack thereof.
In the VCAT decision of Owners Corporation PS 508732B v Fisher [2014] VCAT 1358, the Tribunal found (in relation to a conventionally drawing Plan of Subdivision) that the balcony waterproofing membrane lay within the individual lot property boundary, making it part of the private property of the apartment.
This article is intended to be used for general information only and should not be relied on as formal legal advice. For more specialised advice on building defect claims and your legal rights and responsibilities, do not hesitate to take expert guidance from lawyers well versed in construction law.
Article written by Justin Cotton, Director of Lovegrove & Cotton Pty Ltd
Disclaimer
This article is not legal advice rather a discussion of the topic in only general terms. Should you be in need of legal advice, please contact a construction law firm. The experienced team at Lovegrove & Cotton can help strata communities and owners corporations resolve any type of building dispute.

Wrongful termination of contract
As a construction lawyer, the writer has witnessed many instances where builders and owners find themselves involved in unavoidable litigation due to wrongful termination of contract.
Usually, a well-crafted contract will have a procedure by which the contract can be brought to an end in the event the relationship between the parties breaks down irretrievably due to one party’s breach against the other, however terminating a contract is not always a “get out of jail free card”, as it were. One must be very careful and seek legal advice when considering terminating a contract.
Most contracts provide default provisions to allow parties to resolve their dispute without the need to take the matter to court. This may be issuing a ‘notice of dispute’ to enable parties to engage in dispute resolution discussions and resolve their dispute.
If the matter is not resolved within the dispute resolution period stipulated in the contract (if applicable), then the next step may be issuing a ‘notice of default’. An example of a party’s contractual
default may be carrying out defective building work or poor-quality workmanship by a builder, or failure to pay a progress payment by an owner. The reference to “default” means there must be a default or a substantial breach of the contract that one party is seeking to be remedied by the other party.
It should however be noted that one party’s default does not necessary give the other an automatic right to immediately terminate the contract. In other words, serving a notice of default, does not necessarily entitle a party to terminate the contract, if the default is capable of being remedied and the party in default is willing to remedy the default.
For instance, if a builder fails to rectify an alleged defect within the stipulated time in the notice of default and/or the contract, the owner is still not necessarily entitled to terminate the contract, unless the factual grounds that underpin a right to terminate exist.
Purporting to terminate a contract in circumstances where an innocent party does not give the defaulting party the opportunity to remedy the default described in the default notice, would be regarded as a ‘repudiation’ or unwillingness by the failing party to no longer be bound by the contract or to perform the Contract.
Most contracts also contain a provision that a party seeking to terminate a contract based on a notice of default, should not themselves be in breach of the contract. So the party seeking to terminate due to the fault of the other should have “clean hands”.
Repudiation of contract
Repudiation of contract occurs when a party “evinces an intention to no longer be bound by the contract”, either expressly or by conduct. For instance, a builder may allege that an owner failed to pay a progress payment in circumstances where the relevant building stage has not been completed. If the owner then refuses to pay the alleged progress payment and the builder refuses to continue with the building works, this may be regarded as a repudiation or unwillingness to perform contractual obligations by the builder.
In Heyman v Darwins Ltd 1942, it was held that:
“… a party by words or conduct evinces an intention to no longer to be bound (by the contract) and the other party accepts… and rescinds the contract.”
As mentioned above, every case is different on its merits and one must seek legal assistance prior to terminating a contract, because even if one believes he/she is the wronged party, one can still be liable for wrongfully terminating a contract if due process is not followed pursuant to the contract.
Does repudiation mean the contract is at end?

Repudiation by one party does not automatically end the contract, unless accepted by the other party. Whether to accept a repudiation or insist on specific performance is best answered on a case-by-case basis as each case is different on its facts.
Ending a building contract pursuant to section 41 of the Domestic Building Contracts Act 1995 (Vic) (“DBCA”)
An owner may terminate a major domestic building contract for completion time or cost blows out for unforeseeable reasons if:
(i) The contract price rises by 15% or more after the contract was entered into; or
(ii) The contract has not been completed within 1½ times the period it was to have been completed by.
Furthermore, for the owner to terminate the contract the reason for the increased time or cost was something that could not have been reasonably foreseen by the builder on the date the contract was made.
Any increased time or cost that arises as a result of a prime cost item or a provisional sum or that is caused by a variation are not included in calculating any price rise or increase in time.
To end the contract, the owner must give the builder a signed notice stating that the owner is ending the contract under section 41 of the DBCA and giving details of why the contract is being ended.
If a contract is ended under this section, the builder is entitled to a reasonable price for the work carried out under the contract to the date the contract is ended however the builder cannot recover more than the builder would have been entitled to recover under the contract if it was not ended prematurely.
Lovegrove & Cotton strongly caution owners, builders and contractors to ensure that they do not adopt a layman’s approach to contractual termination.
When faced with the challenges of terminating a building contract, it would be prudent to consult with expert construction lawyers, and have them draft any necessary documents.
Article written by Tsigerda Lovegrove Construction and Planning Lawyer and firm manager Lovegrove & Cotton.
Disclaimer
This article is not legal advice rather a discussion of the topic in only general terms. Should you be in
need of legal advice, please contact a construction law firm. Lovegrove & Cotton Lawyers and
our experienced team will assist you based on the facts and circumstances of your case.
This paper briefly traverses the different approaches to the law regarding caveatable and charging interests in residential building contracting in three Australian jurisdictions. In keeping with the 8 countries of Australia euphemism, each sovereign jurisdiction differs significantly with respect to the ways caveatable interests are treated within the residential contracting setting.
This writer is only venturing into 3 Australian jurisdictions and hazards to say that there may well be other key differences in the remaining 5 Australian jurisdictions that will alter the risk landscape for consumers. It follows that property owners will need to have regard to the apposite provisions in the relevant acts of parliament in the other States and Territories.
Victoria
Until the mid-nineties in Victoria, standard industry building contracts contained charging clauses that allowed the residential building contractor to lodge a caveat on owners property in circumstances where there was a dispute under the contract.
Caveats tended to be lodged when there was a dispute over payment but depending on the wording of the charging clause a very broad licence afforded to the caveator was often permitted in the contractual provision.
The charging clause in the building contract gave the contractor a caveatable interest. Once lodged on the title this had the potential to impact upon the property owners` ability to sell the property until the caveat was removed. So it was a significant encumbrance. Caveats sometimes remained on title until the end of a litigation ie months, years down the line.
When the Domestic Building Contracts Act was promulgated in the mid nineties, the legislation embargoed the builder from having the ability to lodge a caveat on the title, so the lodging of a caveat effectively became illegal.
This legislature introduced the embargo to better protect consumers from circumstances where the charge upon the land imposed significant restrictions upon the owner to deal with the land.
The apposite provision under the said Act is:
Domestic Building Contracts Act 1995 (VIC) Section 18:
- Contract does not entitle builder to put caveat on the title of building site land
- A domestic building contract does not give a builder an estate or interest in any land for the purposes of section 89 of the transfer of Land Act 1958.
The provision exercises an economy of language but its import is clear, builders cannot lodge caveats on the property owner’s title, period.

NSW
The Home Building Act 1989 (NSW) Section 7D also places some limits on the ability of a residential builder to lodge a caveat. But it has to be said the provision isn’t as pithy, as it were, as the Victorian counterpart and unlike the Victorian legislative provision cannot be considered to provide a blanket embargo as there are exceptions.
- Interests in Land under contract
(1) A contract does not give the holder of a contractor licence or any other person a legal or equitable estate or interest in any land, and a provision in a contract or other agreement is void to the extent that it purports to create such an estate or interest.
(2) Accordingly, the holder of a contractor licence or any other person may not lodge a caveat under the Real Property Act 1900 in respect of an estate or interest prohibited by subsection (1).
(3) However, subsection (1) does not apply to a provision in a contract that creates a charge over land if–
(a) the land the subject of the charge is land on which the contract work is, or is to be, carried out, and
(b) the charge is in favour of the holder of a contractor licence who is a party to the contract, and
(c) the charge is created to secure the payment to the holder of the contractor licence by another party to the contract of money due under the contract, but only if a court or tribunal has made an order or judgment that such payment be made, and
(d) in the case of a charge over land under the Real Property Act 1900 –the party to the contract against whom the judgment or order is made is the registered proprietor of the land.
The court has a discretion to permit the lodging of a caveat in the aforesaid circumstances. In this writers` opinion, Section 7D cannot be considered to be unreasonable as it permits the lodging of a caveat once a judgment or order has been made by the Court. Presumably that would serve to prevent rapid sale of a property consequential upon an adverse judgment and an absconding by the owner with the proceeds of sale to prevent payment to the contractor.
ACT
The relevant legislation in the Australian Capital Territory is The Land Titles Act 1925 (ACT) which allows courtesy of Section 104 a person claiming an interest in land to apply to the Land Registrar to have a caveat be entered on that land. The threshold for the initial caveat being placed on the land in question is low under Section 104A(2) with the Registrar ‘not required to determine the validity of a caveator’s claim.’
The legislation does provide a process for a landowner who has had a caveat placed against their land to have that caveat removed. Specifically, Section 107 “Removal of Caveat” requires the landowner to request the Registrar-General to give notice to the caveator for its removal. Once received by the caveator, the caveator has 14 days to seek an order from the Courts that the caveat should remain. The onus at this stage is on to caveator to show that it should not be removed as there is still a serious issue to be tried (GR8 Constructions Pty Ltd v O’Donnell [2011] ACTSC 92 at [26]).
In weighing up these Australian Capital Territory legislative provisions, it is in the writers’ opinion that they ultimately disadvantage property owners. Firstly, the legislation provides very little barriers to any party claiming a registrable interest in land to have a caveat recorded. Secondly, despite the legislation providing a mechanism for landowners to eventually compel the caveator to make an application to the Courts, the caveat is often likely to remain in place so long as in the Courts’ opinion a serious issue to be heard still remains.
Conclusion
In order of hierarchy Victoria clearly affords the greatest level of consumer protection in light of the fact that there is blanket legislative embargo that prevents the lodging of a caveat by the residential builder on the land title. So Victoria is the gold standard.

NSW does not have a blanket embargo but there are hurdles, the main one being the Court is the body that is invested with the power to permit the lodging of a caveat in the above mentioned circumstances.
The ACT does not fair at all well when compared with the other jurisdictions as it provides much greater licence to given parties to lodge caveats on a property owners title.
If the ACT is intent on providing better consumer protection to property owners it would be well advised to harmonise the legislation on point with either NSW or Victoria. As it stands at the moment from a consumer protection point of view it leaves a fair bit to be desired.
Tsigereda Lovegrove, construction lawyer and practice manager at Lovegrove & Cotton has conduct of matters in Victoria, NSW and the ACT.
Lovegrove & Cotton Construction & Planning Lawyers
For thirty years, Lovegrove & Cotton have provided advice and represented property owners, builders, and building practitioners in building and planning regularisation matters. If you wish to engage the firm, feel free to contact us via our website, by emailing enquiries@lclawyers.com.au, or via phone at (03) 9600 4077.
Disclaimer
This article is not legal advice and discusses its topic in only general terms. Should you be in need of legal advice, please contact Lovegrove & Cotton Lawyers and our experienced team will assist you based on the facts and circumstances of your case.
- 1
- 2
- 3
- 4
- Next Page »