Why Building Inspections Should Be Mandatory at Critical Stages and why the IBQC model building act is instructive

27 Nov 2026

By Adjunct Professor Kim Lovegrove

Building inspections should be mandatory by law and carried out by building officials at critical junctures and critical path stages when they can still intervene. That is the approach taken by the IBQC Model Building Act. If a pipe passes through a fire barrier and the gap around it has been left unsealed, the builder can rectify it before the wall is lined. If the defect comes to light down the track, apartment owners may have to raise a special levy just to establish how many apartments are compromised. By then, the cost can include opening and reinstating walls, temporary accommodation, lost rent and litigation over who pays.

Mandatory inspections are building control’s early warning system

A statutory handbrake gives the building official a chance to examine reinforcement before concrete is poured and hardens around it or to inspect the fire barrier before the wall is lined, even when the next trade is ready to start. This is in keeping with the IBQC mantra: build better, not build back better (IBQC principles, Principle Seven).

Directing finite inspection resources to critical stages

Regardless of the jurisdiction, building inspection resources are of course finite. The regulations should direct those resources to the stages at which an official can still intervene and where an overlooked defect could have the gravest consequences. The consequences of failure should determine when the work must be seen and what expertise the inspection demands (Lovegrove, 2020).

The IBQC guidelines distinguish low, medium and high potential consequence. The building official inspects key structural work and returns at completion for low-consequence buildings. Medium-consequence buildings call for structural engineering checks and specialist inspections during commissioning.

For high-consequence buildings, the guidelines add independent expert review of the design and independent inspection during construction and at completion. Where safe evacuation depends on smoke control, for example, the building official can draw on independent scrutiny of the design and on evidence that the installed system performs as intended before deciding whether occupation can proceed (IBQC classification and inspection guidelines, pp. 2-9).

How the IBQC Model Building Act links the code to inspection duties

The IBQC’s remit is the design of best-practice building regulatory guidelines. The adopting jurisdiction is responsible for the technical building code. The IBQC recommends that the code graduate building classifications according to the potential for failure to harm health and safety (IBQC remit; IBQC classification and inspection guidelines, p. 1).

Section 4.2 of the IBQC Model Building Act brings the jurisdiction’s code into the regulatory frame. Section 4.23 requires the relevant building official to carry out the inspections prescribed for the building’s risk classification. The official may carry out additional inspections where necessary (IBQC Model Building Act, ss. 4.2; 4.23).

Under section 4.24, a medium- or high-risk building requires a joint inspection on site before an occupancy permit can issue, unless exempted by regulation. The official convenes the inspection with the owner, builder, building engineer and architect. If they identify a fault, the responsible practitioner must rectify it and a further joint inspection must follow (IBQC Model Building Act, s. 4.24).

I chanced upon the joint inspection protocol while working in China as a senior law reform consultant with The World Bank Group. The team that I was part of was briefing Chinese provincial jurisdictions on international best practice in building regulation. I formed the view that joint inspection was best practice. That experience informed the provision in the IBQC Model Building Act (Lovegrove on the origins of the joint inspection protocol).

The IBQC Model Building Act reserves building permit decisions for public building officials.

When an inspection finds non-compliant work

Under sections 8.1 and  8.2, the building official can give the owner or builder a building notice and must allow a reasonable opportunity to respond. The official must consider any submissions before deciding whether to issue an order.

A building order can “require building work at the building site to cease” and require action “to rectify any non-compliance with the building permit or this Act or the Model Building Regulations”[1]. The order is discretionary. If a danger to life, safety or health makes immediate action necessary, section 8.4 allows an emergency order without first giving notice. Separately, section 8.6 allows the Building Authority to order rectification of defective, non-compliant, incomplete or unsafe work.

Conclusion

Best-practice building regulation will align the inspection schedule with the codified risk classification and give building officials enough capacity to carry it out. Under the regime proposed, the owner will bear the cost of independent review on high-consequence projects. The IBQC Model Building Act provides for the Building Authority to commission and pay the reviewer, and permits it to recoup that expense from the owner or builder (IBQC Model Building Act, s. 2.4).

The official needs to see the work while the builder can still reach it.

About the author

Adjunct Professor Kim Lovegrove Hon D.Litt (WSU), MSE, RML is the inaugural chair of the IBQC. He was the project director of Australia’s National Model Building Act and prepared the drafting instructions for the IBQC Model Building Act, drafted by Gemma Varley. He served as Deputy Executive Director of the Australian Building Codes Board and has advised on international building law reform. He founded Lovegrove & Cotton and practises as a barrister at Forty Eight Shortland Barristers in Auckland. Western Sydney University awarded him an honorary Doctor of Letters in 2025. His book Doctrine of Proportionate Liability is due to be released shortly by Thomson Reuters.

The views expressed in this article are my own. I write in a personal capacity and do not speak on behalf of any organisation with which I am affiliated.

Image Acknowledgements:

The digital renders used in this article were developed collaboratively by Lovegrove & Cotton and ChatGPT


[1] International Building Quality Centre, The IBQC Model Building Act, ss. 8.1-8.2, 8.3-8.4 and 8.6, pp. 36-39. Quoted wording from s. 8.2(4)(c) and (e)(ii), p. 37.

Note:

Under the IBQC Model Building Act, ss. 2.5 and 4.7, building officials employed by the Building Authority or a local authority decide permit applications. Section 2.4 provides separately for independent peer review of prescribed complex projects. In my view, private certification is a poor model for delivering building permits. It demands substantial probity infrastructure, including conflict-of-interest controls, audits and a regulator with the capacity to enforce the rules. See Lovegrove, The Story Behind Two Model Building Acts.