Residential building disputes require more than an assessment of defective workmanship. An owner must identify the correct respondent, the appropriate forum, the applicable time limits and the prospects of recovering the cost of rectification. A regulatory complaint, an insurance claim and civil proceedings serve different purposes. Sometimes all three require attention.
The ACT has avenues for resolving these disputes, but they should not be described simply by importing Victoria’s institutional arrangements. Nor is it accurate to assume that the ACT has neither enforcement powers nor a statutory residential dispute framework. The differences are more specific, and some have significant consequences for litigation strategy.
Comparison with Victoria
Victoria has a specialist domestic building dispute pathway. The Building and Plumbing Commission (BPC) now administers the conciliation service formerly known as Domestic Building Dispute Resolution Victoria. Eligible disputes may proceed through conciliation, with binding dispute resolution orders or a certificate available where appropriate. VCAT’s specialist building jurisdiction continues, although its former Building and Property List is now described as the Land and Environment Division.
The legislative foundation is Part 5 of the Domestic Building Contracts Act 1995 (Vic). Section 56 generally requires a certificate of conciliation before a domestic building work dispute is brought to VCAT, subject to exceptions, including specified urgent applications. Section 57 makes VCAT chiefly responsible for domestic building disputes and provides for a stay of qualifying court proceedings on a party’s application. That rule is subject to qualifications, including federal subject matter that VCAT cannot determine.
Victoria also has a Building Cases List in the County Court. Its existence does not make the County Court and VCAT interchangeable destinations for every homeowner. Jurisdiction, the pleaded causes of action and the statutory stay provisions must be considered before proceedings are issued.
The ACT’s published pathways instead direct ordinary civil claims to ACAT, the Magistrates Court or the Supreme Court, depending on jurisdiction and the amount claimed. They do not identify a counterpart to Victoria’s specialist building list structure. That is a difference in the organisation of dispute resolution, rather than an absence of remedies.
Where does an ACT homeowner go to resolve a residential building dispute?
The practical starting point is to distinguish a request for regulatory intervention from a claim for a private remedy.
For building or planning compliance concerns, the ACT Government directs owners to their building certifier and Access Canberra. For contractual disagreements, it identifies negotiation, the Conflict Resolution Service, ACAT and Access Canberra’s fair trading service as potential avenues. The owner should first put the complaint to the builder in writing, identifying the work, the alleged problem and the response sought.
For an unresolved civil claim, the usual monetary pathways are:
- ACAT: civil claims of $25,000 or less. A larger claim may be heard with the parties’ written agreement, or an applicant may abandon the excess. ACAT expressly recognises building defect disputes and may require a Scott schedule setting out the disputed items.
- ACT Magistrates Court: ordinarily claims above $25,000 and up to $250,000. The Court identifies ss 257 and 266A of the Magistrates Court Act 1930 as relevant to its monetary jurisdiction. [6]
- ACT Supreme Court: unlimited civil monetary jurisdiction, making it the ordinary court destination for claims exceeding the Magistrates Court ceiling.
These amounts are a starting point. The relief sought and any special statutory jurisdiction must also be checked. An owners corporation’s dispute with a builder, for example, should not automatically be treated as an internal unit titles dispute merely because apartments are involved.
Abandoning part of a claim deserves particular care: the convenience of a lower-value forum must be weighed against the recovery being surrendered. Equally, the contract price is not necessarily the amount of the claim. A properly supported assessment of rectification costs and other recoverable loss is needed before choosing the forum.
The ACT’s statutory residential dispute framework
Part 6A of the Building Act 2004 (ACT) provides a residential building dispute framework, including an administrator and dispute resolution processes. It is therefore incorrect to say that the ACT has never legislated a dedicated scheme.
However, legislation and an operational service are different things. ACT Government reform reporting has described work to operationalise the framework, while its public complaints guidance directs owners to the existing pathways discussed above. Those sources do not establish that a generally available Part 6A intake service is operating as at this article’s research date. Access Canberra should confirm availability before an owner relies on that route.
The sound comparison is that Victoria has an identifiable operational conciliation and specialist tribunal determination pathway; the ACT’s statutory framework must be distinguished from the remedies and services an owner can presently access.
Does the ACT Government have enforcement powers?
Yes. The Construction Occupations Registrar has substantive powers under the Construction Occupations (Licensing) Act 2004 (ACT).
Ss 34-38 govern rectification orders. Section 38 permits orders requiring rectification, demolition and the provision of compliant construction services, or the commencement or completion of specified work. Section 39 provides for emergency rectification orders. Ss 40-42 address non-compliance and further action. In appropriate circumstances, the regime also reaches directors and other specified persons: see ss 35(3), 39A and 39B. These powers have statutory preconditions and are not automatic upon a complaint.
A regulator’s enforcement decision does not itself determine every contractual entitlement or compensate an owner for every loss. The practical question is whether the owner needs compliance action, damages, completion of work, or a combination. Regulatory engagement should not be treated as a substitute for assessing a civil claim and its deadline.
Building certifiers and occupancy certification
Victoria uses the statutory expression relevant building surveyor. The building surveyor performs the project’s statutory building surveying functions and ordinarily issues the occupancy permit or certificate of final inspection. Section 43 of the Building Act 1993 (Vic) deals with the decision on an occupancy permit application.
In the ACT, the comparable project role is the certifier, commonly called the building certifier; the practitioner is a licensed building surveyor. ACT Government guidance identifies the certifier’s functions as issuing building approval and the commencement notice, conducting certification inspections and issuing the certificate of completion.
The subsequent occupancy decision is distinct. Section 69 of the Building Act 2004 places the certificate of occupancy function with the Construction Occupations Registrar. The certifier’s completion certificate under section 48 is a separate document.
Owners should therefore obtain both the certification records and the occupancy documentation. They should not assume that the officer who inspected the work also issued the final occupancy authorisation. Nor should occupancy certification be confused with a contractual assurance that every aspect of the work is defect-free. Victoria expressly distinguishes suitability for occupation from proof of full statutory compliance in section 46.
Limitation periods
Victoria
Section 134(1) of the Building Act 1993 generally prevents a building action being brought more than ten years after the occupancy permit, or, if none was issued, the certificate of final inspection. Ss 129-130 define the relevant scope.
The cladding extension is conditional. Section 134(2) allows qualifying cladding building actions more than ten but less than fifteen years after the relevant certificate, where the ordinary bar fell on or after 16 July 2019 and before 1 December 2023. Those are expiry dates, not a window for issuing occupancy permits. Section 134(2A) also recognises extensions under section 77 of the VCAT Act.
ACT
Section 142 of the Building Act 2004 (ACT) sets a ten-year building-action limit, measured first from the completion certificate; failing that, the last certifier inspection; failing both, first occupation or use. Subsection (2) adds a separate trigger associated with the end of a certifier’s appointment. Subsection (3) preserves shorter limitation periods under other Territory laws.
Section 11 of the Limitation Act 1985 (ACT) ordinarily provides six years from accrual of the cause of action. Accrual requires analysis of the particular claim: breach of contract and negligence should not simply be assumed to share the same starting date. Section 40 provides a discretionary extension mechanism for latent property damage and associated economic loss. It is not a general promise of fifteen years to sue, nor should an owner assume it displaces a separate Building Act bar.
There is also the statutory warranty period. Section 88(4) of the Building Act 2004 (ACT) read with regulation 38 of the Building (General) Regulation 2008 (ACT), provides six years for structural elements and two years for non-structural elements, measured from the statutory completion day. The regulation’s “structural” definition includes external wall components, including weatherproofing. These warranty periods must be distinguished from the limitation period for commencing a particular cause of action.
The ACT therefore requires several dates to be checked together. A ten-year building-action provision does not necessarily leave an owner ten years to bring every claim. A complaints process should not be assumed to stop any relevant clock.
Proportionate liability: are ACT consumers exempt?
Under section 107B(3)(b) of the Civil Law (Wrongs) Act 2002 (ACT), a consumer claim is excluded from Chapter 7A. Section 107C principally requires a claim by an individual concerning goods or services supplied for personal, domestic or household use, subject to its exclusions. An owners corporation or company should not assume it meets that definition.
But there is a separate building-action apportionment regime in ss 140-141 of the Building Act 2004.
The judicial treatment of that regime is critical. In Hyblewski v Bellerive Homes Pty Ltd [2019] ACTSC 44 at [123]-[124], the Supreme Court explained, following Dunn v Hanson Australasia Pty Ltd [2017] ACTSC 169, that section 141 permits apportionment between defendants. After the proceedings against the builder had been discontinued, only one defendant remained against whom the relevant finding could be made; section 141 apportionment was consequently unavailable.
The ACT consumer exclusion therefore cannot safely be presented as a blanket exemption from all proportionate liability in residential construction litigation. The applicable regime must be identified before advising an owner about recovery or a defendant about joinder.
How does an owner navigate the consumer exemption?
The analysis should proceed claim by claim. First, identify the claimant and the purpose for which the goods or services were supplied. A residential address alone does not establish a consumer claim under section 107C. An individual homeowner, an investor, a company and an owners corporation cannot simply be placed in the same category. The facts must support the statutory definition and address its exclusions.
Second, identify each cause of action, the loss claimed and the basis on which each proposed defendant is said to be liable. If the claim is a consumer claim, record why Chapter 7A is excluded by section 107B(3)(b). Then separately ask whether the damages claim is a building action within section 140 and whether section 141 applies. Passing the consumer test answers the Chapter 7A question; it does not answer the Building Act question.
Third, assess the parties and recovery before joining, settling with or discontinuing against anyone. Hyblewski demonstrates why the defendants remaining in the proceedings matter under section 141. It is not a universal instruction to sue only one participant: liability must still be proved, and settlement terms, releases, costs and the remaining defendant’s ability to satisfy a judgment require separate attention. Where Chapter 7A applies, its treatment of absent concurrent wrongdoers and its notice provisions must instead be considered on their own terms.
The practical result should be a written assessment identifying the regime applicable to each claim, the parties required for the proposed relief and the risk that part of the loss will remain unrecovered. The consumer exemption is a point for legal analysis, not an assurance of full recovery.
In Victoria, Part IVAA of the Wrongs Act 1958 (Vic) contains no equivalent general consumer-claim exemption. Ss 24AF-24AI govern apportionable claims, including specified reasonable-care and misleading-conduct claims. This does not mean every contractual or statutory warranty claim is automatically apportionable.
Must every concurrent wrongdoer be joined?
The ACT’s general regime permits consideration of an absent concurrent wrongdoer: ss 107F(2)(b) and 107F(4). That proposition must not be transferred uncritically to the separate Building Act regime discussed above.
Victoria’s section 24AI(3) generally prohibits consideration of a non-party’s comparative responsibility, unless the person is absent because they have died or, for a corporation, have been wound up. Mere insolvency is not the stated exception. Section 24AL addresses joinder; section 24AE defines defendant broadly enough to include another party joined otherwise than as plaintiff.
This is more precise than saying that every conceivable participant must be joined before apportionment can operate. The issue is whose comparative responsibility the decision-maker is legally permitted to consider. In either jurisdiction, a litigation strategy needs to distinguish a defendant, a third party and a person who remains outside the proceedings.
Must a defendant identify other potential wrongdoers?
ACT section 107G concerns a defendant with reasonable grounds to believe another person may be a concurrent wrongdoer. Failure to provide prompt written particulars of identity and involvement can attract costs, including indemnity costs, where the claimant unnecessarily incurs costs through ignorance of that person’s possible responsibility. It is not a duty to identify every imaginable defendant in every building claim.
Victoria’s Part IVAA has no direct counterpart to section 107G. That does not dispense with pleading, disclosure or procedural obligations arising elsewhere. The sound comparison concerns this particular statutory notice-and-costs mechanism.
Is residential building insurance mandatory?
ACT
Yes, for qualifying insurable residential building work. The framework includes ss 37(4), 84, 87 and 90 of the Building Act and regulation 37 of the Building (General) Regulation. The regulation excludes work costing less than $12,000 from Part 6.
The ACT Government describes mandatory cover for houses and apartment buildings of no more than three storeys, excluding a car park, through an authorised insurer or approved fidelity fund. The builder obtains the cover before the commencement process, and the certifier checks it. This is not universal cover for all residential development, particularly higher-rise buildings.
For current settings, regulation ss 39-41 specify $200,000 minimum insurance cover, a five-year insurance period and a 180-day claim period. The relevant statutory triggers and the particular policy or fidelity certificate must also be checked. The Government explains that the claim-notification period starts when the owner becomes aware of the builder’s insolvency, death or disappearance. Mandatory cover should not be mistaken for insurance responding to every defect while a builder remains trading.
Victoria
The comparison must now distinguish older DBI policies from the Home Warranty scheme operating from 1 July 2026.
BPC guidance states that older DBI generally applied to eligible domestic work over $16,000 and responded to specified builder events, commonly death, disappearance or insolvency. Existing DBI policies do not convert into Home Warranty. For eligible contracts signed on or after 1 July 2026, Home Warranty applies to eligible work exceeding $20,000 and provides broader assistance where a builder fails or refuses to complete or rectify work the subject of a Rectification Order, subject to the scheme’s requirements. The stated maximum assistance is $400,000 per home.
The new statutory scheme is in Part 9A of the Building Act 1993, including section 137O concerning payment of premiums. Contract dates, building eligibility and transitional arrangements must therefore be checked before selecting the insurance route.
Preparing an ACT building claim
A useful first file contains the contract and variations, approved plans, certifier appointment and inspection records, completion and occupancy certificates, insurance documents, correspondence and dated photographs. Technical advice should identify the defect, its cause, an appropriate rectification method and a supported cost.
Before proceedings, the owner and adviser should then settle four questions: who has the right to claim; against whom; for what relief; and by when. This is particularly important for common property, multiple responsible practitioners and claims involving an insolvent builder.
Conclusion: limitation and apportionment require particular care
An ACT homeowner has avenues for regulatory intervention, negotiation, court or tribunal proceedings and, for eligible claims, insurance or fidelity fund assistance. But identifying an available forum is only the beginning. The published ACT pathways do not identify a dedicated building list equivalent to Victoria’s specialist arrangements, and the owner must navigate several interacting statutory regimes.
In our view, the limitation provisions present a particularly dangerous trap for an owner who assumes that “ten years” is the time available to sue. The ACT position cannot safely be reduced to one period running from one certificate. Section 142 has alternative and additional triggers and expressly preserves shorter periods under other Territory laws. Accrual under the Limitation Act, the statutory warranty periods and any available extension require separate examination. The apparent simplicity of a ten-year provision can conceal an earlier deadline.
The practical response is an early, documented limitation analysis for every proposed claim and defendant. Obtain the completion certificate, inspection history, occupation records and any notice ending a certifier’s appointment; establish the relevant breach and damage dates; and distinguish warranty duration from the deadline for commencing proceedings. Where a date or legal characterisation remains uncertain, investigate it urgently and plan around the earliest reasonably arguable deadline while that uncertainty is resolved. Negotiations, a regulatory complaint or an insurance inquiry should never be assumed to preserve the right to sue.
The consumer exemption presents a second trap. An owner may correctly establish that Chapter 7A of the Civil Law (Wrongs) Act does not apply, yet still confront the Building Act’s separate apportionment provisions. Advice that stops at “consumers are exempt” is therefore incomplete. The necessary sequence is to establish consumer status, classify each claim, examine ss 140-141 independently, and assess the consequences of joinder, settlement and discontinuance before those decisions are made.
For the homeowner, these are questions about whether a claim survives and how much of a proven loss can actually be recovered. Careful analysis of time limits and apportionment belongs at the start of an ACT residential building dispute, before procedural or settlement choices narrow the available remedies.
About the authors
Justin Cotton is a Director of Lovegrove & Cotton and heads the firm’s practitioner advocacy practice. For nearly 20 years he has represented builders, building surveyors and building certifiers in disciplinary proceedings, and he appears at VCAT and NCAT. His practice is cross-jurisdictional: he is instructed by building practitioners and small to medium enterprises in NSW, Victoria, the ACT and Queensland. He chairs the HIA Victorian Industrial Relations and Legal Services Committee, is admitted in Australia and New Zealand, and was named in Global Law Experts 2024 for construction law in Australia.
Tsigereda Lovegrove is a Construction and Planning Lawyer and Manager at Lovegrove & Cotton. She conducts matters in VCAT, NCAT, the County Court and Supreme Court, and the Building Appeals Board. She is a Board Member of the International Building Quality Centre and Secretary of its Dispute Resolution Coalition, and an Adjunct Fellow at Southern Cross University. She was named in Global Law Experts 2024 for construction law in Australia, and advises in English and Amharic.
Disclaimer
This article is general information only and is not legal advice. It reflects the law and regulator guidance in Victoria and the ACT as at October 2026. Obtain advice specific to your situation before acting.
Image Acknowledgements:
The digital renders used in this article were developed collaboratively by Lovegrove & Cotton and ChatGPT

The World Organization of Building Officials (WOBO) has acknowledged the work of Lovegrove & Cotton for their recent contributions to the International Building Quality Centre (IBQC). WOBO noted the firm’s involvement (in a WOBO update dated 28 March 2024) regarding IBQC guidelines, stating, “WOBO appreciates the work carried out by Lovegrove and Cotton and their recent updates in respect of IBQC.”
Members of the Lovegrove & Cotton team have been instrumental in assisting with the development of the IBQC Risk-Based Building Classification and Mandatory Inspection Guidelines. These guidelines were developed over 18 months, involving collaboration with leading professionals from the United States, United Kingdom, Australia, New Zealand, and Germany. The guidelines focus on implementing a risk-based approach to building classification and mandatory inspection processes.
On 28 March 2024, three key articles authored by Lovegrove & Cotton were republished by WOBO:
- IBQC Risk-Based Building Classification and Mandatory Inspection Guidelines – Details the collaborative effort in developing these guidelines.

- The New IBQC Risk-Weighted Building Classification and Mandatory Inspection Guidelines – So Compellingly Logical – Discusses the rationale behind a risk-based approach to building codes.

- 15 Core Elements of Best-Practice Building Regulation Highlights the essential components that contribute to effective building regulations.

Lovegrove & Cotton acknowledges WOBO’s recognition and is very grateful. The firm also recognizes the important role that this highly regarded global body plays in advancing good practice approaches to building regulation and building control.
Lovegrove & Cotton will continue to support the development of robust building regulatory frameworks, in line with a tradition of helping to establish good practices in building control dating back more than 30 years.
Image Acknowledgements:
The digital renders used in this article were developed collaboratively by Lovegrove & Cotton and ChatGPT. The photo images that are not the digital renders are stock images sourced from Shutterstock.

A Profile on Tsigereda Lovegrove From Ethiopia to Australia, from Amharic to English and from Admin to running a legal practice – the journey to date and continuing
Tsigereda left Ethiopia in 2009. After an initial period of 4 months in Auckland, New Zealand, with her late mother-in-law, Tsigereda Lovegrove settled in Australia. She learned English as her second language and set her sights on a career in law.
Building a Career at Lovegrove & Cotton
Starting as a receptionist at Lovegrove & Cotton Lawyers in 2011, Tsigereda worked her way up within Lovegrove & Cotton, which was established in 1993 by the writer.
Balancing Education and Professional Responsibilities
While working at the firm, Tsigereda embarked on an LLB at Victoria University. She balanced her studies with her role as Office Manager and Financial Controller, overseeing the firm’s financial and administrative operations. This experience laid a solid foundation for her future roles.
Transitioning to Legal Practice
After completing her law degree, Tsigereda became a Construction Lawyer and Practice Manager at Lovegrove & Cotton. With 11 years of management experience, she now oversees practice management, ensuring the firm’s operations run efficiently while fostering a positive work environment. Since she became Practice Manager, the firm has grown by 300% in terms of full-time legal personnel.
Legal Expertise in Construction Law
Tsigereda’s legal practice covers a broad spectrum of construction law, including tribunal and court cases, building appeals, and building regulatory compliance in Victoria and NSW. She also provides advice on legislative interpretation of the Building Act 1993 and the Domestic Building Contracts Act.
Recognition of her expertise is reflected in the law firm being named in the construction section of Globe Law Experts 2024 for Australia.
International and Local Contributions
In addition to her domestic legal work, Tsigereda serves as Secretary to the International Building Quality Centre (IBQC) Dispute Resolution Coalition. She coordinates efforts among a distinguished group of international legal experts, including senior jurists from Africa and Australia, as well as eminent construction lawyers from both hemispheres. In this capacity, she contributes to the development of dispute resolution protocols and building regulatory guidelines for emerging economies. She is also a member of the Victorian Building Disputes Practitioners Society Committee.
Her commitment to Africa in terms of the work she does on emerging economy guidelines is an intergenerational commitment to capacity development in Africa, as her grandfather-in-law worked for UNESCO in the 1950s and 60s in Addis in educational capacity building. The late Norman Lovegrove was instrumental in helping to establish mobile schooling where UN VW Combis transported teachers to the rural regions to make education more accessible.

Publications and Thought Leadership
Tsigereda has authored and co-authored several publications, focusing on key issues such as building insurance requirements, risk-based building classification, and inspection protocols for emerging economies.
Some Thoughts on Tsigereda Lovegrove’s Contributions
“In the short time I have known Tsigereda ‘Ziggy’ Lovegrove, I have come to respect her diligence, capabilities, and tenacity. Set against the backdrop of a faraway homeland, Ziggy forged a new life for herself in Australia, conquered the English language, and raised a family. In her professional life, Ziggy is rightfully proud to have attained a law degree and become a protégé of the law firm that bears her husband’s name. Professionally, she has assisted the International Building Quality Centre in conducting background research, synthesizing material, and coordinating some of the logistics of international meetings, which has demonstrated her dexterity in familiarizing herself with topics that one can only imagine were quite foreign to her not so long ago.”
– Neil Savery, IBQC Board Member
“ In my interactions with Tsigereda, I have found her to be a remarkable force of intelligence, integrity, and professionalism. At the IBQC, she skillfully facilitated teamwork, ensuring that collaboration was smooth, insightful, and effective. Her exceptional communication and leadership skills were evident in these interactions.
Her extensive knowledge and research contributions on mediation as a dispute resolution mechanism have made a significant positive impact on the industry. Additionally, her strategic thinking and dedication to enhancing dispute resolution mechanisms in developing countries, such as Ethiopia, have left a lasting impression on me”.
– Judge/Justice Maedot Yeshak Tesfaye, Federal Court of Ethiopia .
The Future

Tsigereda is intent on growing the practice in Australasia, opening a New Zealand office, and continuing to participate in the development of building regulatory guidelines that are contextualized for Africa. Her commitment to advancing the industry reflects her dedication to making a positive difference both locally and globally.
This piece is penned by the founder of Lovegrove & Cotton Kim Lovegrove

Introduction
It is 30 years since the proclamation of the Victorian Building Act 1993. Unbeknownst to some, it was based on a national microeconomic initiative—the National Model Building Act. Here’s some background:
The Model Building Act, initiated by the Australian Uniform Building Regulatory Co-ordinating Council (AUBRCC) in 1990, marked a pivotal shift in how building regulations were developed in parts of Australia.This initiative aimed to create a unified, efficient framework that could address the inefficiencies and inconsistencies prevalent in the building industry at the time. By incorporating best practices from around the world and focusing on key reforms such as liability capping, compulsory insurance, and private certification, the Model Building Act sought to set new benchmarks in construction regulation and consumer protection.
AUBRCC – the Catalyst
In 1990, the Australian Uniform Building Regulatory Co-ordinating Council (AUBRCC) initiated the creation of a National Model Building Act to streamline building regulations nationwide.
The Rationale for the Project and the Problems with Building Regulation in the Early Nineties
The push for national uniformity aimed to cut costs and increase efficiency by addressing conflicting regulations, which were costly and inefficient for interstate developers, builders and building practitioners. This push was triggered by the national microeconomic regime encouraged by the special premiers’ conference an initiative pioneered by the late Prime Minister Bob Hawke.
The Aims of the Project
- Develop a world-class model of building regulation.
- Reform construction liability laws.
- Establish efficient appeal mechanisms for building permits.
- Introduce private certification for building permits.
The Methodology
The project was apolitical and driven by a national microeconomic reform initiative, which was a broader effort to improve the efficiency of the Australian economy. The process began with extensive international analysis, involving the selection of best practice concepts from abroad, such as the ten-year liability capping and compulsory insurance models from France, and adapting them to fit the Australian context.
Consultation
Extensive consultations with industry stakeholders, local governments, and trade associations ensured comprehensive input. Stakeholders provided preferences for reforms, including liability capping, proportionate liability, and private certification.
Drafting Instructions and a Model Act
Drafting instructions were prepared for parliamentary counsel, specifically the NSW Office of the Chief Parliamentary Counsel, leading to the creation of the Model Building Act. The Model Act was then distributed to key stakeholders nationwide.
What then Happened?
While the Model Building Act did not become a uniform national law, its key principles were adopted by various jurisdictions over the next decade, significantly influencing building regulations.
The Northern Territory
The NT was the first to adopt the Model Building Act, introducing private building approvals, liability capping, compulsory registration, and insurance for building practitioners.
Victorian Building Act 1993
Victoria followed, implementing a mandatory registration system for key and defined building practitioners. This system required practitioners to be qualified in their respective disciplines, have experience in their vocations, and carry compulsory insurance.
Proportionate Liability: Proportionate liability allocated responsibility among multiple parties based on their contribution to the loss. This ensures each party only pays their fair share, promoting fairness and accountability.
Ten-Year Liability Capping: This limited the period for claims against building practitioners to ten years from the issue of an occupancy permit for the completed building work. It offers certainty and reduces long-term risks for construction professionals, aiding in managing insurance premiums.
NSW
NSW introduced ten-year liability capping and proportionate liability in the late 90s. The state also established a registration system for key building practitioners, although only private certifiers were required to register under this system.
What Was So Pioneering About the Model Building Act?
The Act introduced proportionate liability, ten-year liability capping, compulsory insurance, private certification, and a more efficient dispute resolution system for building permit delivery.
So Did the Model Building Act Reshape Modern Day Building Control in Some Jurisdictions?
Dr. Anthony Lavers a British expert in construction law and building regulation, commented on the profound impact of the Model Building Act, stating: “The reforms in Victoria and New South Wales were nothing short of groundbreaking and set a new benchmark for building control.” Lavers made this observation during a presentation at a construction law conference in 2005. Although uniform legislation was not achieved, the Act provided a law reform template that several jurisdictions adopted. It introduced essential reforms like proportionate liability and compulsory insurance, which improved consumer protection.
Conclusion
The Model Building Act was profound because it introduced pioneering concepts like proportionate liability and compulsory insurance. These reforms significantly reduced local government liability exposure, improved efficiency, and set new standards for building regulations, shaping modern-day building control in parts of Australia. By addressing some of the inefficiencies and inconsistencies of previous regulations, the Act established a more equitable and efficient framework for the construction industry, laying the groundwork for future reforms in building regulation.
Author
This article was authored by Adjunct Professor Kim Lovegrove, who served as the Project Director for the Model Building Act project. He later became the instructing officer to parliamentary counsel in Victoria while serving as the Assistant Director of Building Control during the development of the Building Act 1993.
Disclaimer:
The information provided in this article is for general informational purposes only. It is not legal advice. The views expressed in this article are those of the author only and are not to be taken as reflecting the views of any affiliated organizations or entities.